00:00:00.140 --> 00:00:06.880
<v Noel Brown>The pause that exempts its biggest project.
Episode 28. October 30th, 2026. Hosted</v>

00:00:06.980 --> 00:00:11.440
<v Noel Brown>by Noelle. New York announced the nation's
first statewide data center moratorium in</v>

00:00:11.460 --> 00:00:15.860
<v Noel Brown>July. The largest data center proposal in
the state's North Country may never face</v>

00:00:15.900 --> 00:00:20.600
<v Noel Brown>it. That gap is not a bug someone discovered
after the fact. It is written into the</v>

00:00:20.660 --> 00:00:26.820
<v Noel Brown>order itself, and it is where this episode
starts. Ellis Ward at rftuv.ai published</v>

00:00:26.880 --> 00:00:32.540
<v Noel Brown>a full landscape examination of New York's
data center pause on October 29th, 2026.</v>

00:00:33.200 --> 00:00:38.140
<v Noel Brown>That article is the spine of what follows.
Ellis covers AI systems and the policy</v>

00:00:38.180 --> 00:00:42.800
<v Noel Brown>instruments that govern them, and his lens
here is precise. What does a moratorium</v>

00:00:42.840 --> 00:00:47.360
<v Noel Brown>on one agency's discretionary permits
actually do to a queue measured in gigawatts?</v>

00:00:48.100 --> 00:00:52.620
<v Noel Brown>The answer, as you will hear, is less than
the headline suggests and more than the</v>

00:00:52.660 --> 00:00:57.060
<v Noel Brown>industry's loudest critics of the pause
will admit. Three acts: the instrument, the</v>

00:00:57.100 --> 00:01:02.540
<v Noel Brown>place, and the stakes. On July 14th, 2026,
Governor Kathy Hochul signed Executive</v>

00:01:02.640 --> 00:01:07.180
<v Noel Brown>Order number sixty-two. The full title
is worth saying aloud. Establishing a</v>

00:01:07.240 --> 00:01:11.400
<v Noel Brown>temporary moratorium on data centers in
New York while the state develops higher</v>

00:01:11.540 --> 00:01:15.560
<v Noel Brown>standards for data center development and
benefits blueprint to support localities.</v>

00:01:16.140 --> 00:01:21.340
<v Noel Brown>Her office described it as the nation's
first statewide data center moratorium. The</v>

00:01:21.360 --> 00:01:24.980
<v Noel Brown>description is accurate, and the carve-outs
are substantial, and you need both</v>

00:01:25.040 --> 00:01:29.040
<v Noel Brown>halves to understand what happened.
Here is the mechanism. The Department of</v>

00:01:29.080 --> 00:01:33.480
<v Noel Brown>Environmental Conservation will not issue
new discretionary permits or approvals for</v>

00:01:33.520 --> 00:01:38.600
<v Noel Brown>data centers that consume or can consume
fifty megawatts or more, but only for</v>

00:01:38.660 --> 00:01:43.360
<v Noel Brown>applications not yet deemed complete before
the order took effect. Any application</v>

00:01:43.400 --> 00:01:48.520
<v Noel Brown>the DEC had already deemed complete before
July 14th escapes the pause entirely.</v>

00:01:49.240 --> 00:01:53.480
<v Noel Brown>Facilities supporting manufacturing,
research, education, or medical care are</v>

00:01:53.500 --> 00:01:58.320
<v Noel Brown>exempt. A group of facilities on contiguous
sites counts as a single data center</v>

00:01:58.660 --> 00:02:03.200
<v Noel Brown>when calculating whether the fifty-megawatt
threshold is crossed. Three limits stack</v>

00:02:03.240 --> 00:02:08.259
<v Noel Brown>together. One agency, one threshold, one
application window. The order does not</v>

00:02:08.320 --> 00:02:12.700
<v Noel Brown>touch local permitting at all. Towns
retain full authority to approve or block</v>

00:02:12.780 --> 00:02:18.220
<v Noel Brown>projects, whatever the state does. The
pause binds the DEC. It does not bind a town</v>

00:02:18.240 --> 00:02:22.900
<v Noel Brown>board. The pause runs until the Department
of Public Service finalizes a generic</v>

00:02:22.960 --> 00:02:28.580
<v Noel Brown>environmental impact statement through
the Energize NY proceeding, case 26 E zero</v>

00:02:28.780 --> 00:02:33.860
<v Noel Brown>zero four five, the large load
interconnection reform case the PSC opened on</v>

00:02:33.900 --> 00:02:40.060
<v Noel Brown>February 12th of this year. On September
17th, the PSC issued a positive declaration</v>

00:02:40.100 --> 00:02:46.240
<v Noel Brown>and a draft scope. Public comments were
due October 20th. The GEIS examines energy</v>

00:02:46.300 --> 00:02:51.060
<v Noel Brown>demand, water use and quality, air
quality, disproportionate impacts on</v>

00:02:51.080 --> 00:02:56.340
<v Noel Brown>disadvantaged communities, and noise. How
long does the GEIS take? The governor's</v>

00:02:56.400 --> 00:03:01.060
<v Noel Brown>office says up to a year. Jones Day, which
analyzed the order's text, notes that the</v>

00:03:01.120 --> 00:03:06.740
<v Noel Brown>order itself states no one-year cap. The
timeline is open. Energize NY, the doctrine</v>

00:03:06.800 --> 00:03:11.200
<v Noel Brown>underneath the pause, was announced in
Hochul's January 13th State of the State</v>

00:03:11.260 --> 00:03:16.520
<v Noel Brown>address. Its logic is direct. Data centers
will either pay more for their energy or</v>

00:03:16.600 --> 00:03:20.780
<v Noel Brown>supply their own. Now look at what the
legislature tried to do before the governor</v>

00:03:20.860 --> 00:03:25.440
<v Noel Brown>acted. State Senator Kristen Gonzalez
sponsored the Responsible Data Center</v>

00:03:25.520 --> 00:03:31.440
<v Noel Brown>Development Act. It passed both chambers
on June fourth, 2026. The governor did not</v>

00:03:31.500 --> 00:03:36.120
<v Noel Brown>sign it. What would it have done? A
one-year moratorium starting at twenty</v>

00:03:36.220 --> 00:03:41.800
<v Noel Brown>megawatts, not fifty. Public hearings
in host communities. A DEC environmental</v>

00:03:41.940 --> 00:03:46.820
<v Noel Brown>impact report. New electric and water
rate classes for facilities above twenty</v>

00:03:46.900 --> 00:03:52.720
<v Noel Brown>megawatts. Efficiency goals above five
megawatts. A host community benefit program</v>

00:03:52.780 --> 00:03:58.160
<v Noel Brown>above twenty megawatts. Labor standards
above five megawatts. The bill passed both</v>

00:03:58.200 --> 00:04:02.360
<v Noel Brown>chambers and has never been signed. The
executive order that came instead reaches a</v>

00:04:02.400 --> 00:04:07.080
<v Noel Brown>higher threshold, binds one agency, and
leaves local authority untouched. Senator</v>

00:04:07.160 --> 00:04:11.400
<v Noel Brown>Gonzalez applauded what followed from the
order anyway. In October, Empire State</v>

00:04:11.460 --> 00:04:15.420
<v Noel Brown>Development released a community investment
framework under a sixty-day direction in</v>

00:04:15.460 --> 00:04:20.140
<v Noel Brown>the order. Gonzalez said,"This summer I
visited thirteen communities across the</v>

00:04:20.200 --> 00:04:24.100
<v Noel Brown>state fighting hyperscale data centers,
and it was clear that from Brooklyn to</v>

00:04:24.140 --> 00:04:28.120
<v Noel Brown>Buffalo, communities are looking for
long-term investment and a seat at the table."</v>

00:04:28.800 --> 00:04:33.200
<v Noel Brown>The community investment framework from
Empire State Development is voluntary. This</v>

00:04:33.240 --> 00:04:37.700
<v Noel Brown>is not a small detail. The framework is
a template that localities may use and</v>

00:04:37.760 --> 00:04:42.540
<v Noel Brown>modify. Its central benchmark, a recommended
community investment of one million</v>

00:04:42.600 --> 00:04:47.660
<v Noel Brown>dollars per megawatt, means a fifty-megawatt
facility carries a recommended fifty</v>

00:04:47.760 --> 00:04:51.580
<v Noel Brown>million dollar investment, potentially
through a locally managed community</v>

00:04:51.620 --> 00:04:57.780
<v Noel Brown>investment fund. The menu covers roads,
water and sewer, parks, transit, housing,</v>

00:04:58.060 --> 00:05:04.060
<v Noel Brown>training, schools, childcare, broadband,
public safety, small business support, and</v>

00:05:04.120 --> 00:05:09.320
<v Noel Brown>vacant property revitalization. Good
neighbor commitments address water, noise,</v>

00:05:09.580 --> 00:05:14.380
<v Noel Brown>lighting, and design, with prevailing
wages and structured local hiring. The</v>

00:05:14.440 --> 00:05:19.200
<v Noel Brown>framework advises caution on developer
non-disclosure agreements and calls for early</v>

00:05:19.240 --> 00:05:24.060
<v Noel Brown>resident engagement and annual reporting
after opening. ESD President Hope Knight's</v>

00:05:24.160 --> 00:05:29.100
<v Noel Brown>stated rationale for the benchmark, data
centers are not major local job generators.</v>

00:05:29.700 --> 00:05:33.860
<v Noel Brown>The benchmark is how the framework tries
to translate infrastructure demand into</v>

00:05:33.920 --> 00:05:38.760
<v Noel Brown>something a town can point to over time.
But the framework recommends, it does not</v>

00:05:38.800 --> 00:05:44.080
<v Noel Brown>require. No regulatory floor attaches to
the one million dollar figure. Governor</v>

00:05:44.140 --> 00:05:48.140
<v Noel Brown>Hochul, in the release accompanying the
framework, said,"In the absence of federal</v>

00:05:48.200 --> 00:05:51.880
<v Noel Brown>leadership, someone has to write the
rules, and New York is leading the way."</v>

00:05:52.500 --> 00:05:56.020
<v Noel Brown>Separately, the Department of Public
Service is considering a New York grid</v>

00:05:56.100 --> 00:06:00.620
<v Noel Brown>acceleration fund and a requirement that
data centers fund new clean generation</v>

00:06:00.760 --> 00:06:05.736
<v Noel Brown>dedicated to their operations. The governor
is also pursuing legislation to repeal</v>

00:06:05.916 --> 00:06:11.016
<v Noel Brown>state sales tax exemptions for large data
centers. That repeal is a pursuit, not a</v>

00:06:11.036 --> 00:06:15.396
<v Noel Brown>completed action. To understand what the
pause means on the ground, you need to know</v>

00:06:15.436 --> 00:06:20.516
<v Noel Brown>how large the queue already is. Ellis
Ward's article uses NYISO figures as the</v>

00:06:20.556 --> 00:06:25.616
<v Noel Brown>primary spine, and so does this episode.
Other tallies exist and are not directly</v>

00:06:25.656 --> 00:06:29.796
<v Noel Brown>comparable. When they appear, the source
travels with the number. According to</v>

00:06:29.876 --> 00:06:34.935
<v Noel Brown>NYISO, the large load interconnection
queue grew from six projects totaling one</v>

00:06:35.016 --> 00:06:39.496
<v Noel Brown>thousand and forty-five megawatts in
twenty twenty-two to twenty-nine projects</v>

00:06:39.596 --> 00:06:44.176
<v Noel Brown>totaling nearly six thousand and fifty-five
megawatts as of July twenty twenty-five.</v>

00:06:44.916 --> 00:06:49.156
<v Noel Brown>New York's operating base is about two
hundred and sixty-four megawatts compared</v>

00:06:49.176 --> 00:06:54.196
<v Noel Brown>with more than seventeen gigawatts
operating in Virginia. NYISO's power trends</v>

00:06:54.236 --> 00:06:58.056
<v Noel Brown>expects more than two thousand five
hundred megawatts of additional large load</v>

00:06:58.096 --> 00:07:03.116
<v Noel Brown>demand by twenty thirty-five. Forecasters
anticipate roughly two thousand five</v>

00:07:03.176 --> 00:07:07.676
<v Noel Brown>hundred to four thousand megawatts of queued
demand actually reaching the system by</v>

00:07:07.735 --> 00:07:12.196
<v Noel Brown>twenty thirty-five. For a sense of how
other tallies compare, Hardware Busters</v>

00:07:12.296 --> 00:07:16.916
<v Noel Brown>tallied at least twenty-five proposals
totaling roughly nine thousand three hundred</v>

00:07:16.936 --> 00:07:21.636
<v Noel Brown>and forty megawatts, and a Tribune Content
Agency count found thirty-eight proposed</v>

00:07:21.736 --> 00:07:26.456
<v Noel Brown>projects at roughly eleven thousand nine
hundred megawatts. Those figures are not</v>

00:07:26.496 --> 00:07:31.316
<v Noel Brown>comparable to NYISO's count. They use
different methodologies, different stages of</v>

00:07:31.356 --> 00:07:36.456
<v Noel Brown>development, different definitions of what
counts as a proposal. The NYISO numbers</v>

00:07:36.496 --> 00:07:41.336
<v Noel Brown>are the spine. The gap between what is
queued and what the pause actually catches is</v>

00:07:41.376 --> 00:07:45.896
<v Noel Brown>where the Instrument Act and the PLACE Act
meet. Consider the two cases that define</v>

00:07:45.936 --> 00:07:50.836
<v Noel Brown>this episode's geography. Massena, St.
Lawrence County. NYDIG and its affiliate</v>

00:07:50.976 --> 00:07:56.676
<v Noel Brown>North Country Colocation Services, or NCCS,
propose a one point five million square</v>

00:07:56.796 --> 00:08:01.536
<v Noel Brown>foot, six hundred and thirty-five megawatt
data center on the former Alcoa East site</v>

00:08:01.836 --> 00:08:06.716
<v Noel Brown>near the St. Lawrence River. This is, as
reported by North Country Public Radio, the</v>

00:08:06.776 --> 00:08:11.275
<v Noel Brown>largest North Country proposal in the
state. Six hundred and thirty-five megawatts</v>

00:08:11.335 --> 00:08:16.596
<v Noel Brown>is about seventy percent of the Moses-Saunders
hydroelectric dam's output. NCCS</v>

00:08:16.636 --> 00:08:20.876
<v Noel Brown>projects roughly two hundred permanent
jobs and becoming one of the town's largest</v>

00:08:20.936 --> 00:08:26.376
<v Noel Brown>taxpayers. Massena drew roughly ten data
center proposals by May twenty twenty-six.</v>

00:08:26.976 --> 00:08:31.816
<v Noel Brown>The town board voted three to two against
a six-month local moratorium. Here's the</v>

00:08:31.856 --> 00:08:37.516
<v Noel Brown>detail the order's carve-outs make
significant. NCCS says it needs no new DEC</v>

00:08:37.656 --> 00:08:42.236
<v Noel Brown>permits because it applied in twenty twenty.
A twenty twenty application would place</v>

00:08:42.276 --> 00:08:46.776
<v Noel Brown>this proposal, the state's largest North
Country proposal, inside the complete</v>

00:08:46.836 --> 00:08:51.436
<v Noel Brown>application exemption. The pause would
never apply. St. Lawrence County Planning</v>

00:08:51.496 --> 00:08:55.956
<v Noel Brown>Director Jason Fottenhauer has said the
exemption could be legitimate. This is</v>

00:08:55.996 --> 00:09:00.896
<v Noel Brown>reported and claimed. It has not been
adjudicated. Former Mayor James Heidi supports</v>

00:09:00.956 --> 00:09:05.896
<v Noel Brown>development. Former Public Works
Superintendent Hassan Fayad has noted years of</v>

00:09:05.936 --> 00:09:10.416
<v Noel Brown>economic struggle in the town. The five
votes on the town board split three to two</v>

00:09:10.456 --> 00:09:14.696
<v Noel Brown>in favor of letting proposals proceed.
That vote is a local authority decision,</v>

00:09:14.956 --> 00:09:19.676
<v Noel Brown>exactly the kind the executive order left
untouched. Now come south and east. East</v>

00:09:19.796 --> 00:09:24.536
<v Noel Brown>Fishkill, Duchess County. This show's
own county. Treetop Companies explored a</v>

00:09:24.576 --> 00:09:29.256
<v Noel Brown>roughly one gigawatt campus, more than one
million square feet on about one hundred</v>

00:09:29.276 --> 00:09:33.396
<v Noel Brown>and forty-three acres on a wooded site
near homes, a daycare, and a house of</v>

00:09:33.416 --> 00:09:38.476
<v Noel Brown>worship. The project surfaced in the state
grid queue before Treetop made any formal</v>

00:09:38.536 --> 00:09:43.216
<v Noel Brown>approach to the town. Residents were
protesting a project that had not formally</v>

00:09:43.276 --> 00:09:48.616
<v Noel Brown>arrived at Town Hall. East Fishkill is a
former IBM semiconductor center. A four</v>

00:09:48.656 --> 00:09:53.576
<v Noel Brown>hundred and sixty-acre IBM campus operated
there for nearly fifty years. The town</v>

00:09:53.616 --> 00:09:58.216
<v Noel Brown>has about thirty thousand people. One
reported comparison put the Treetop campus's</v>

00:09:58.236 --> 00:10:03.196
<v Noel Brown>projected electricity use at more than the
city of Buffalo uses, a city of about two</v>

00:10:03.236 --> 00:10:07.956
<v Noel Brown>hundred and seventy-five thousand people.
Resident and professor Tanya Radford said,</v>

00:10:07.956 --> 00:10:11.996
<v Noel Brown>"We're at this moment where things are
happening very quickly. We need to get our</v>

00:10:12.016 --> 00:10:15.796
<v Noel Brown>ducks in a row and think about the various
ways in which data centers and new energy</v>

00:10:15.896 --> 00:10:20.516
<v Noel Brown>usage will affect our long-term community,
cohesiveness, environmental quality, and</v>

00:10:20.595 --> 00:10:25.456
<v Noel Brown>character." In late June twenty twenty-six,
the East Fishkill Town Board adopted a</v>

00:10:25.516 --> 00:10:30.016
<v Noel Brown>unanimous three-year moratorium on data
centers over twenty megawatts running to</v>

00:10:30.056 --> 00:10:34.836
<v Noel Brown>July twenty twenty-nine. He board used the
authority the executive order explicitly</v>

00:10:34.896 --> 00:10:40.096
<v Noel Brown>left with towns. In October twenty twenty-six,
Treetop Companies formally challenged</v>

00:10:40.136 --> 00:10:44.356
<v Noel Brown>that moratorium, according to reporting.
The challenge has not been decided.</v>

00:10:44.836 --> 00:10:48.876
<v Noel Brown>Brookhaven on Long Island followed East
Fishkill with an eighteen-month moratorium</v>

00:10:48.916 --> 00:10:53.256
<v Noel Brown>of its own. Same policy from Albany.
Opposite ends of the state. Opposite local</v>

00:10:53.376 --> 00:10:58.536
<v Noel Brown>outcomes so far. Massena voted against
a local moratorium. East Fishkill voted</v>

00:10:58.596 --> 00:11:03.376
<v Noel Brown>unanimously for one. The complete application
exemption may mean the state pause</v>

00:11:03.436 --> 00:11:08.336
<v Noel Brown>never applied to Massena's largest proposal
at any point. In East Fishkill, the</v>

00:11:08.396 --> 00:11:13.176
<v Noel Brown>state pause exists in theory, but the
town's own three-year moratorium now runs</v>

00:11:13.216 --> 00:11:18.296
<v Noel Brown>longer and starts lower at twenty megawatts
against the state's fifty. Massena and</v>

00:11:18.396 --> 00:11:23.176
<v Noel Brown>East Fishkill are not the whole map. Niagara
County has five operating complexes and</v>

00:11:23.296 --> 00:11:28.416
<v Noel Brown>five more proposed in Niagara Falls alone.
Stream Data Centers proposes a six point</v>

00:11:28.436 --> 00:11:32.936
<v Noel Brown>three billion dollar, two hundred and
fifty megawatt campus at STAMP in Genesee</v>

00:11:33.036 --> 00:11:37.216
<v Noel Brown>County, projecting more than one thousand
construction jobs and more than one</v>

00:11:37.256 --> 00:11:42.036
<v Noel Brown>hundred and twenty long-term positions
with closed loop air cooling. TerraWolf</v>

00:11:42.136 --> 00:11:47.056
<v Noel Brown>proposes a four hundred megawatt Cayuga
campus in Lansing on the former Cayuga power</v>

00:11:47.156 --> 00:11:51.876
<v Noel Brown>plant site. Hearings in Lansing drew
near unanimous community opposition, and</v>

00:11:51.956 --> 00:11:57.096
<v Noel Brown>operations are not expected before roughly
twenty twenty-nine. Behind every megawatt</v>

00:11:57.156 --> 00:12:01.616
<v Noel Brown>in the queue is an accounting question,
and the accounting question is, who pays?</v>

00:12:02.216 --> 00:12:06.176
<v Noel Brown>Utilities recover infrastructure investment
through rates. Grid upgrades built to</v>

00:12:06.216 --> 00:12:10.436
<v Noel Brown>serve large new loads get spread across
all customers unless the rules assign those</v>

00:12:10.496 --> 00:12:16.906
<v Noel Brown>costs to the load that caused
them. Case 26E0045, the Energize NY</v>

00:12:17.026 --> 00:12:21.526
<v Noel Brown>Interconnection proceeding, is built on
the beneficiary pays principle. If you need</v>

00:12:21.566 --> 00:12:26.506
<v Noel Brown>the grid upgrade, you pay for it. JD
Supra's analysis of the pause notes that as</v>

00:12:26.546 --> 00:12:30.826
<v Noel Brown>utility bills climbed, data centers became
a symbol of the affordability squeeze.</v>

00:12:31.346 --> 00:12:35.386
<v Noel Brown>The governor framed the pause inside an
affordability campaign in the run-up to the</v>

00:12:35.406 --> 00:12:40.266
<v Noel Brown>November third election. The connection
between rate design and politics is direct.</v>

00:12:40.906 --> 00:12:45.386
<v Noel Brown>Cost allocation is a technical proceeding.
It is also a story about who gets the</v>

00:12:45.426 --> 00:12:50.506
<v Noel Brown>bill. Water is the other arithmetic. How
much a data center uses depends almost</v>

00:12:50.566 --> 00:12:55.266
<v Noel Brown>entirely on how it cools. Reported
ranges put evaporative cooling systems at</v>

00:12:55.366 --> 00:13:00.146
<v Noel Brown>hundreds of thousands to millions of
gallons per day. Closed loop systems run at</v>

00:13:00.206 --> 00:13:05.426
<v Noel Brown>roughly twenty-two thousand gallons per
day. The GEIS scope covers water use and</v>

00:13:05.526 --> 00:13:09.946
<v Noel Brown>quality, and the executive order directed
an assessment of water withdrawal rules.</v>

00:13:10.686 --> 00:13:15.546
<v Noel Brown>Stream Data Center's closed loop design in
Genesee County is a deliberate departure</v>

00:13:15.586 --> 00:13:19.966
<v Noel Brown>from the evaporative norm. The spread
between the two approaches is not a technical</v>

00:13:20.106 --> 00:13:25.046
<v Noel Brown>footnote. It is several orders of magnitude.
Jobs are where the economic argument</v>

00:13:25.066 --> 00:13:30.106
<v Noel Brown>for data centers runs into its own limits.
A typical hyperscale facility generates a</v>

00:13:30.166 --> 00:13:35.206
<v Noel Brown>few dozen permanent positions. Construction
phases generate hundreds to more than a</v>

00:13:35.246 --> 00:13:40.106
<v Noel Brown>thousand jobs per project. The tension
between those two numbers sits in the middle</v>

00:13:40.146 --> 00:13:45.326
<v Noel Brown>of every host community negotiation. In
post-industrial towns carrying years of</v>

00:13:45.366 --> 00:13:50.186
<v Noel Brown>fiscal strain, a major new taxpayer matters
in ways permanent headcount does not</v>

00:13:50.246 --> 00:13:55.606
<v Noel Brown>show. The tax base can outlast the
construction crew. The permanent jobs number is</v>

00:13:55.686 --> 00:14:00.846
<v Noel Brown>real and small. ESD's community investment
framework acknowledges that tension</v>

00:14:00.886 --> 00:14:06.346
<v Noel Brown>directly. The one million dollar per megawatt
benchmark is not a job substitute. It</v>

00:14:06.386 --> 00:14:10.846
<v Noel Brown>is a mechanism to translate the infrastructure
demand a large facility places on a</v>

00:14:10.886 --> 00:14:15.486
<v Noel Brown>community into durable investment that the
community controls. Whether it works as</v>

00:14:15.526 --> 00:14:20.166
<v Noel Brown>designed depends on whether the framework
is used, and it is voluntary. On the</v>

00:14:20.206 --> 00:14:26.106
<v Noel Brown>question of who is on which side, Ellis
Ward's article at rftuv.ai maps the</v>

00:14:26.166 --> 00:14:31.106
<v Noel Brown>landscape. For development, developers,
host town officials who see tax base and</v>

00:14:31.206 --> 00:14:36.246
<v Noel Brown>payroll, including Messina's board majority,
and construction labor. Patrick Kelly,</v>

00:14:36.446 --> 00:14:40.426
<v Noel Brown>speaking for the County Industrial
Development Authority, cautions that proposals</v>

00:14:40.446 --> 00:14:45.706
<v Noel Brown>are potential activity, not commitments.
Against or skeptical, host community</v>

00:14:45.806 --> 00:14:50.146
<v Noel Brown>residents in Lansing, East Fishkill,
and elsewhere. Environmental litigants,</v>

00:14:50.266 --> 00:14:55.266
<v Noel Brown>including Earth Justice in the North
Tonawanda proceeding. Senator Gonzalez and the</v>

00:14:55.306 --> 00:14:59.726
<v Noel Brown>bill's sponsors, whose more stringent
measure the order effectively displaced.</v>

00:15:00.286 --> 00:15:05.306
<v Noel Brown>Representative Alexandria Ocasio-Cortez,
who has introduced federal legislation for</v>

00:15:05.346 --> 00:15:10.046
<v Noel Brown>a national moratorium. And industry critics
who warn that permitting uncertainty</v>

00:15:10.406 --> 00:15:14.686
<v Noel Brown>will redirect investment to states that
have not paused. The governor's posture is</v>

00:15:14.726 --> 00:15:19.206
<v Noel Brown>conditional welcome. On October sixth, at
a roundtable in East Fishkill, she stood</v>

00:15:19.246 --> 00:15:24.206
<v Noel Brown>with Representative Ocasio-Cortez and
Representative Pat Ryan and said,"Our job is</v>

00:15:24.266 --> 00:15:28.846
<v Noel Brown>not to protect the profits of billion-dollar
corporations. My job is to protect New</v>

00:15:28.886 --> 00:15:33.326
<v Noel Brown>Yorkers." The roundtable was in East
Fishkill. This shows county where the town had</v>

00:15:33.406 --> 00:15:39.046
<v Noel Brown>already voted unanimously to pause on its
own. Close. What did the pause pause? The</v>

00:15:39.086 --> 00:15:43.386
<v Noel Brown>generic environmental impact statement has
no fixed deadline. The governor's office</v>

00:15:43.426 --> 00:15:48.966
<v Noel Brown>says up to a year. Jones Day notes the
order's text states no cap. The legislature's</v>

00:15:49.006 --> 00:15:52.906
<v Noel Brown>Responsible Data Center Development Act
passed both chambers and has never been</v>

00:15:52.986 --> 00:15:58.086
<v Noel Brown>signed. The tax exemption repeal is a
pursuit, not an action. The community</v>

00:15:58.126 --> 00:16:02.606
<v Noel Brown>investment framework is voluntary, and its
one million dollar per megawatt benchmark</v>

00:16:02.646 --> 00:16:07.926
<v Noel Brown>is persuasive rather than binding. The PSC
cost allocation proceedings are ongoing,</v>

00:16:08.566 --> 00:16:12.426
<v Noel Brown>and the complete application exemption
means some of the largest proposals in the</v>

00:16:12.506 --> 00:16:16.846
<v Noel Brown>state may never face the conditions the
pause is meant to establish because their</v>

00:16:16.906 --> 00:16:21.866
<v Noel Brown>paperwork crossed the right desk before
July fourteenth. Ellis Ward's article closes</v>

00:16:21.906 --> 00:16:28.346
<v Noel Brown>on a question, and it is the right one.
What exactly did the pause pause? The honest</v>

00:16:28.406 --> 00:16:33.226
<v Noel Brown>answer is some portion of new applications
above fifty megawatts from one agency's</v>

00:16:33.265 --> 00:16:38.146
<v Noel Brown>docket for an undefined period while a
grid reform proceeding runs its course and</v>

00:16:38.166 --> 00:16:43.186
<v Noel Brown>while towns decide for themselves whether
to go further, stop short, or wait. East</v>

00:16:43.286 --> 00:16:48.506
<v Noel Brown>Fishkill went further, three years, twenty
megawatts unanimously. Messina stopped</v>

00:16:48.566 --> 00:16:53.146
<v Noel Brown>short, three to two against any local
pause, and the largest proposal there may</v>

00:16:53.226 --> 00:16:58.266
<v Noel Brown>carry a twenty twenty application date that
puts it outside the state pause too. New</v>

00:16:58.306 --> 00:17:02.586
<v Noel Brown>York announced a moratorium and built the
exemptions into the instrument. The towns</v>

00:17:02.626 --> 00:17:06.926
<v Noel Brown>are filling the space between what the
order says and what it does. Whether that is</v>

00:17:06.986 --> 00:17:11.626
<v Noel Brown>enough, whether the generic environmental
impact statement lands before the queue</v>

00:17:11.706 --> 00:17:15.906
<v Noel Brown>outgrows the question it was meant to
answer, whether the legislature's bill ever</v>

00:17:15.946 --> 00:17:20.586
<v Noel Brown>returns from the table where it has been
sitting since June fourth, whether the tax</v>

00:17:20.646 --> 00:17:25.486
<v Noel Brown>exemption repeal clears the chamber, whether
Treetop's challenge to East Fishkill's</v>

00:17:25.546 --> 00:17:31.386
<v Noel Brown>moratorium succeeds, whether NCC's claim
about its twenty twenty application holds</v>

00:17:31.446 --> 00:17:36.586
<v Noel Brown>under scrutiny. None of these are settled.
What is settled is the order's text and</v>

00:17:36.626 --> 00:17:41.066
<v Noel Brown>the text limits, and the fact that a
queue measured in gigawatts was already in</v>

00:17:41.126 --> 00:17:46.226
<v Noel Brown>motion when the order was signed. Pausing
the permits did not pause the queue. The</v>

00:17:46.286 --> 00:17:51.666
<v Noel Brown>question the GEIS is meant to answer, who
the grid is for and who pays for it, was</v>

00:17:51.746 --> 00:17:56.746
<v Noel Brown>already the most consequential open question
in New York energy policy before July</v>

00:17:56.806 --> 00:18:01.866
<v Noel Brown>fourteenth. The pause made it official.
This is reporting from the Uncanny Valley.</v>

00:18:02.146 --> 00:18:06.906
<v Noel Brown>I'm Noelle. The analysis in this episode
draws on Ellis Ward's October twenty-ninth</v>

00:18:07.066 --> 00:18:13.666
<v Noel Brown>landscape examination at rftuv.ai, the
governor's office, Jones Day, NYISO,</v>

00:18:14.106 --> 00:18:19.286
<v Noel Brown>North Country Public Radio, Empire State
Development, and JD Supra as sourced in</v>

00:18:19.346 --> 00:18:21.226
<v Noel Brown>Ellis' article. We'll be back.</v>